Cogeneration Unit Piping

Manufacture and assembly of piping routes and auxiliary steel structures for a new cogeneration unit with an electrical output of 999 kWe and a thermal output of 1018 kWt in an existing gas boiler house in Prague - Řepy.

The piping routes for condensate, chilled, cooling, heating, and return water, urea, and natural gas were executed in various diameters up to DN 200, using both carbon steel and stainless steel.

The work included the necessary non-destructive testing of welds, pressure tests, surface protection, and insulation.

Implementation period: 11/2021 – 03/2022

What we did

For more information, please do not hesitate to contact us. Contact us.

Our Contact

This website uses cookies.

We use cookies to personalize content and ads, provide social media features and analyze our traffic. We also share information about the use of our site with our social media, advertising and analytics partners. They may use the data together with other information they collect about you while using their services.

Deny all
Show details
Allow all